Batajnica Health Center Cost Jumps to 1.7 Billion Dinars
How much will the new health center in Batajnica cost? The contract signed today puts the price at 1.7 billion dinars, more than double the June figure.

How much will the new health center in Batajnica actually cost? Serbia’s Ministry of Public Investments signed a reconstruction contract today worth 1.7 billion dinars, roughly 14.5 million euros at the current exchange rate. That is more than double the figure the same minister announced just two months ago.
The contract was signed by Minister of Public Investments Darko Glisic, at the Government of Serbia building, together with Drazena Babic, director of the Zemun Health Center, and a representative of the construction contractor. The project covers reconstruction of a satellite facility in Batajnica that currently operates as a branch of the Zemun Health Center. The deadline for completing the works is 600 days from the start of construction.
The current building went up in 1964 and, according to the minister, has long been too small for the needs of the local population. The new facility will measure around 4,038 square meters, which Glisic said is three times the space available today.
“The total area of this facility, which was built back in 1964, will be as much as three times larger than what exists now. So we are tripling the number of square meters and the usable space available to the people working in this health facility, and that area will be around 4,038 square meters. This will genuinely create conditions for this facility to outgrow the status of a satellite unit within a health center, perhaps even to become independent in that sense, because it will truly have both the equipment and enough space for all the residents of Batajnica and everyone who uses this health facility to feel good, comfortable,” Glisic said after the signing.
The goal, then, is not just a bigger building. The facility is meant to stop functioning as a satellite unit and to operate as an independent health institution.
When should the health center be finished?
The works have a 600 day deadline from the start of construction, so roughly a year and a half from the moment the machinery actually moves onto the site. The exact start date of construction was not disclosed in the contract.
Why is the price double the original announcement?
There is some history behind this, and the figures differ quite a bit depending on when they were stated.
- In June, after meeting with the leadership of the Zemun municipality, Glisic announced a figure of around 830 million dinars (about 7.1 million euros) for the reconstruction, with a deadline by the end of 2027. That plan included demolishing the existing building, constructing an entirely new health facility and a separate transformer station, and the public procurement process was announced to begin in early June.
- Earlier, when the project received its construction permit, the Batajnica Info portal reported an investment of 725 million dinars (about 6.2 million euros).
- The contract signed today stands at 1.7 billion dinars, more than double the June estimate.
There is no official explanation for the difference in the available statements. It is possible the final price includes items that were not part of the earlier announcement, but this has not been specified anywhere.
Gavrilo Kovacevic, president of the Zemun municipality, had earlier described the project, at a meeting in June, as one of the most important for Batajnica, while director Babic said at the time that the new facility would be “representative in every respect” and that the institution was counting on expanded capacity, equipment and staff.
For the residents of Batajnica, this currently means one practical thing: the contract is signed, the 600 day deadline is official, and whether the completion date lands closer to the fall of 2027 or some later year will depend on when the machinery actually moves onto the construction site.