Hungary Pipeline: 5.5 Million Tons vs Serbia's 3.3 Million
The planned Hungary to Novi Sad pipeline will carry 5.5 million tons of oil a year, nearly double Serbia's 3.3 million ton use. Babic warns that alone won't fix things if MOL takes over NIS.

The planned pipeline running from the Hungarian border to Novi Sad is designed to carry around 5.5 million tons of crude oil a year. Serbia, according to an estimate from Milun Babic, president of the Assembly of the Association of Energy Experts of Serbia, uses about 3.3 million tons annually. The gap of nearly two million tons is the first hard number attached to a project that, until now, had mostly been discussed through deadlines and political announcements.
Serbia’s parliament has approved a proposal to guarantee borrowing for Transnafta ad Pancevo, the company carrying out the project. Transnafta issued the construction tender in late December. The route runs from Horgos to the Novi Sad Terminal, with the section on Serbian territory longer than 100 kilometers.
Mining and Energy Minister Dubravka Djedovic Handanovic said on August 26 that work should begin before the end of the year.
“The plan was for construction to start in the fall, but we’ll see, given all the procedures currently underway,” Djedovic Handanovic said.
According to both biznis.rs and B92, construction is expected to take about two and a half years to complete, though neither source specifies the calendar year the pipeline is expected to be finished.
Why one pipeline isn’t enough
Serbia, Babic points out, currently has practically only one channel for supplying oil and oil derivatives.
“Serbia currently has practically only one channel for supplying oil and oil derivatives, and that’s the JANAF pipeline, which runs from Omisalj to Pancevo,” Babic told Euronews Serbia.
The new route would bring in oil via Hungarian territory, along the path of the Druzba pipeline, opening up a second supply channel. The minister applies the same diversification logic to gas.
“We’ll keep the JANAF supply going, but the pipeline with Hungary can also stand on its own,” Djedovic Handanovic said.
“What matters for energy security, and we did the same thing with gas pipelines, is not relying on a single supply route,” the minister said, adding that dependence on imports can never be reduced to zero, since Serbia doesn’t produce enough of its own oil and gas.
Babic warns that building the pipeline alone won’t solve every problem, particularly if Hungary’s MOL were to eventually become the majority owner of the Oil Industry of Serbia (NIS).
“It’s never good to keep all your cards in one pocket,” Babic said, pointing to the need for greater diversification of supply sources and routes.
We covered this question earlier, in the article NIS and Russian Gas: Serbia Awaits Two Decisions by September 30, where the ownership structure of NIS was flagged as an open question with a direct bearing on the country’s energy security.
Is there a longer term solution?
As a longer term direction, Babic proposes extending the link south, toward Thessaloniki. The stretch from Skopje to Thessaloniki, he says, has already been rebuilt and operates as a product pipeline, so only the link from Serbia to Skopje would be missing.
“Then we could say we’d truly be gentlemen about it. Europe would value us far more too, because establishing another supply line matters a great deal to it, not just for this Balkan section, but for central Europe as well,” Babic said.
The energy expert also pointed to the importance of the Danube for energy supply, since low water levels make river transport of oil and its derivatives harder.
“And if the Danube doesn’t rise, we’ll always be in something of a crisis,” Babic warned.
As a risk to the Hungary pipeline actually going ahead, Babic cites possible political change in Hungary, though he doesn’t think that would necessarily have to slow the work down. He also mentions land expropriation along the route as a possible source of delay.
“There are always various unforeseen events,” Babic said, adding that he still considers the minister’s announced deadline reasonable.
For now, the only certainties are the ones already on paper: a capacity of 5.5 million tons, consumption of 3.3 million, and the guarantees Serbia’s parliament has already approved for Transnafta’s borrowing. Whether the second supply channel actually cuts Serbia’s dependence on a single route will also depend on who owns NIS two and a half years from now.