Djurdjevica Tara Bridge damaged by night crossing
Montenegro's Traffic Administration says an unauthorized crossing damaged waterproofing already installed on the bridge. The traffic ban officially runs until October 26.

In neighboring Montenegro, someone crossed the Djurdjevica Tara Bridge overnight between October 1 and 2, even though it has been closed to all traffic since August 10 for repairs, and damaged a layer of waterproofing that had already been installed. That is according to a statement from Montenegro’s Traffic Administration, which warns that further crossings could disrupt the work schedule on one of the best-known bridges in the country.
What did the Traffic Administration say about the damage?
According to the statement, the damage happened overnight and will require additional repairs:
“Last night, due to an unauthorized crossing of the bridge, the layer of waterproofing that had previously been installed was damaged, so the damage must be repaired additionally.”
The Administration says every new attempt to cross could cause further damage and extra costs, and could slow down the work. It urges citizens and all road users to respect the temporary regime and the posted signs:
“The Traffic Administration appeals to citizens and all road users not to attempt to cross the Djurdjevica Tara Bridge while the works are underway, because such attempts can endanger people’s safety and also damage the work already completed.”
In the same statement, the Administration reminds the public why the bridge is being repaired. The works, it said, aim to restore the bridge and extend its service life, and to make the route safer and more reliable. It describes the bridge as an important tourist attraction.
When does the bridge reopen, and what was announced earlier?
Officially, the traffic suspension is in force until October 26 at noon. Earlier, in a statement to RTCG, Radojica Poleksic of the Traffic Administration spoke about room for an earlier reopening:
“The traffic suspension is defined until October 26, until 12:00. We are currently about 10 days ahead of that deadline, so we expect it to be around October 10.”
That estimate predates this incident. The Administration does not repeat it in the new statement and does not say it still holds, so October 26 remains the official deadline. The statement also gives no figure for how large an area was damaged or how long the additional repairs will take.
Poleksic also laid out the order of the remaining work at the time. All structural elements of the bridge had been repaired, the deck still had to be prepared for waterproofing, then asphalt would follow, and after that work on the railing, cornices and curbs. The current statement implies that the waterproofing has since been installed, and that is exactly the layer that has now been damaged.
Who is hit hardest by the closure?
The Djurdjevica Tara Bridge is the only link between Pljevlja and Zabljak. Bus operators from Pljevlja now take the motorway over the Slijepac Bridge toward Podgorica, and one line has been cancelled. Bus operator Boban Radulovic described the consequences to RTCG:
“We cut one line. We are barely keeping the rest going. In the morning at 7:20 we go to the Slijepac Bridge, by motorway to Podgorica, and at 15:20 we also go by motorway. We are moving both lines to the motorway. Our costs are big, our expenses are big.”
Among the comments from residents that RTCG recorded was this one: “Even with 200 km extra, I will get to Podgorica or to Belgrade by motorway faster than I will get to Zabljak.” According to the same report, the closed road makes daily trips to work, school and other errands harder for residents of both municipalities.